Progress on Re-Digging the Footers

Progress on Re-Digging the Footers

After a long weather delay, they got back to work on Friday, March 2. They started re-digging the footers and pumping the water out of them. The geotextile fabric and loads of gravel were delivered. What is the fabric? The fabric is Thrace-Linq® 125EX. I 

Back to Work! Starting on the Engineered Footers

Back to Work! Starting on the Engineered Footers

It is March and they are finally working on our house again! Woo Hoo! The last time they were out there was on January 17th. We got the Engineer’s Excavation Report on January 22nd and gave them an additional check to keep going. We pulled 

Schumacher Homes Model in Asheville, North Carolina

Schumacher Homes Model in Asheville, North Carolina

It has been so long since we started building, I kinda forgot what the model looks like. I’ve been visualizing the house we are building, which is similar, but mirror reversed. I drove out to walk around it again, spend some time and check out 

Still Bad Weather… No Change But Another Dumpster

Still Bad Weather… No Change But Another Dumpster

It is Sunday, February 4. I woke up to the sound of freezing rain on the skylight. When I first came here, this was all swamp. Everyone said I was daft to build a castle on a swamp, but I built it all the same, 

Excavation Report – Engineered Footings

Excavation Report – Engineered Footings

So, the engineer has been out to the land and has issued his Excavation Report. We are going to have to put in Engineered Footings. The standard footings are included in the cost of the house. We have to pay extra for anything beyond this. 

Putting in the Driveway, Ditch and Culverts

Putting in the Driveway, Ditch and Culverts

The house will have a cement driveway, but they are putting in a construction driveway that will cross the gully to where Cliff will put the barn. The gravel driveway is pretty wide. It’s got a ditch on the right side. It is raised and 

Driveway Progress, Footers Draining, Clearing Up

Driveway Progress, Footers Draining, Clearing Up

January 15th: I went down to see how things are going. It is wet, muddy and very cold, but they got a lot done. They scraped and leveled the driveway and put in a drainage ditch. They put in two culverts. They dug a trench 

Building Our New Schumacher Home:  Foundation Construction

Building Our New Schumacher Home: Foundation Construction

They are working on our footings and foundation today. The contractor came out to dig trenches for frost footings. What should have been one foot is about four feet. They have to keep digging till they get past the mud. They dig. Poke with a 

Building a New House – Digging the Footers

Building a New House – Digging the Footers

They started digging the footers today. Around 11:00 the builder called. The grader had called him and said he was not hitting stable ground. He had already gone down as far as is typical, but was hitting soft soil and clay. The first contractor had 

Building Our New Schumacher Home:  Build

Building Our New Schumacher Home: Build

The Schumacher Homes website says the Build stage should take 21 – 25 weeks. They got off to a great start. The day after we closed on the loan, they started pulling the permits. “There are varying degrees of homesite preparation necessary depending on your